Project Schedule

Smithville ISD 2016 Bond Program
 
Athletic Complex
 
Project Kick-off                
January 2017
Schematic Design          
January 2017 - July 2017
Design Developments      
April 2017 - September 2017
Contract Documents        
August 2017 - September 2017
Bidding / Permitting        
September 2017 - October 2017
Construction    
November 2017 - July 2018
 
Junior High Campus 
 
Project Kick-off
January 2017
Schematic Design
July 2017 - September 2017
Design Development
August 2017 - October 2017
Contract Documents
October 2017 - February 2018
Bidding / Permitting
March 2018 - April 2018
Construction             
April 2018 - July 2019
 
Main Campus Renovations
 
Project Kick-off                
May 2018
Schematic Design          
May 2018 - June 2018
Design Development      
July 2018 - August 2018
Contract Documents      
September 2018 - October 2018
Bidding / Permitting        
November 2018 - December 2018
Construction                  
January 2019 - August 2019