Smithville Independent School District Committed to Excellence

Skip to main content
Mobile Menu
Homecoming is this Friday, September 9th ■ Get Connected with Smithville ISD's Phone App at www.myschoolway.com/smithvilleisd
School Board » Bond 2016 » Construction Updates

Construction Updates

Smithville ISD will post updates in this location as construction on the multi-purpose athletic complex and the new junior high campus begins.
Architectural rendering for the multi-purpose athletic complex with concession and restroom facilities.
(Updated as of November 10, 2017)
 
Construction Updates from PBK
Friday, August 9, 2019
 
Site seating installed       screen display
Site seating installed at exterior.                  Screen display programmed at marquee.
 
Friday, August 2, 2019
 
Gym floor graphic       counter shutter installed
Gym floor graphics installed.                Counter shutter installed at concession.
 
Friday, July 26, 2019
 
Building graphics
Building graphics installed.
 
Friday, July 19, 2019
 
Parking lot asphalt     New drive construction
Parking lot asphalt installation ongoing.     New drive construction ongoing.Friday, July 12, 2019
 
Tile installation     Locker installation
Tile installation in Area D is ongoing.        Locker installation in Area D is ongoing.
 
 
 
Friday, June 28, 2019
 
Carpet Installation     Gym walls
Carpet installation is ongoing.          Gyp. bd. walls in gym are ongoing.
 
Friday, June 21, 2019
 
Gym flooring installation     Locker installation
Wood flooring installation in gym is ongoing.     Locker installation is ongoing.
 
Wenger instrument storage     Kitchen equipment installation
Wenger instrument storage is installed.     Kitchen equipment installation is ongoing.
 
Friday, June 14, 2019
 
Tile installation main corridor     Alluminum door installation
Tile installation in Main Corridor is ongoing.    Aluminum door installation is ongoing.
 
Friday, June 7, 2019
 
Marquee installation     Wall tile installation
Marquee installation is ongoing.     Wall tile installation at kitchen ongoing.
 
Stage wood flooring     Ceiling in main corridor
Stage wood flooring installation ongoing.       Ceiling in main corridor complete.
Friday, May 31, 2019
 
Acoutic wall panel installation     Dirt work at new drive
Acoustic wall panel installation is ongoing.        Dirt work at the new drive is ongoing.
 
 
Friday, May 24, 2019
 
Painting     LVT Installation
Paint installation is ongoing.      LVT installation at academic corridors is ongoing.
 
Friday, May 17, 2019
 
Ramp installation     Pyramid diffusers
Ramp installation has commenced.               Pyramid diffusers installed at Band.
 
Friday, May 10, 2019
 
Acoustic wall panel installation      VCT Installation
Acoustic wall panel installation has commenced.      VCT installation has commenced.
 
Friday, April 26, 2019
 
Stage repainting     Plumbing fixture installation
Stage repainting complete.      Plumbing fixture installation on going.
 
Science Lab Casework     Front entry flatwork
Science Lab casework installation is ongoing.       Front entry flatwork is ongoing.
 
Friday, April 19, 2019
 
Front Entry Glazing       Sidewalk Installation
Front entry glazing installation on going.      Sidewalk installation on going.
 
Friday, April 12, 2019
 
Casework Installation      Column wrap in corridor
Casework installation is ongoing.      Column wrap in main corridor ongoing.
 
Friday, April 5, 2019
 
Front Entry      Marquee Sign
Front entry masonry installation ongoing.    Marquee sign installation ongoing.
 
Friday, March 29, 2019
 
Tile Installation    Mechanical Pad
Tile installation is ongoing.    Mechanical pad concrete installation is ongoing.
 
Friday, March 22, 2019
 
Installation    Tile Installation
Gyp. Bd. installation in gym ongoing.         Tile Installation ongoing.
 
Friday, March 15, 2019
 
Ceiling     Framing
Lay-in ceiling installation ongoing in Library.  CMU and gyp. bd. framing ongoing in Area D.
 
Friday, March 8, 2019
 
Main Corridor    CMU - Gym
Main corridor gyp. bd. and framing ongoing.  CMU and gyp. bd. framing ongoing in Gym.
 
Friday, March 1, 2019
 
Cafeteria     Gym framing
Cafeteria gyp. bd. and framing ongoing.  CMU and gyp. bd. framing ongoing in Gym.
 
Friday, February 22, 2019
 
Library Roughin      Electrical Room
Library mechanical rough-in and furr downs.      Electrical room rough-in ongoing.
 
Friday, February 15, 2019
 
Entry Canopy     Athletic Area
Entry canopy feature framing installation is wrapping up.  Athletic area interior CMU installation is ongoing.
 
Friday, February 8, 2019
 
construction photo
Exterior masonry installation is ongoing.
 
construction photo
Athletic area interior CMU installation is
ongoing.
 
Friday, February 1, 2019
 
construction photoExterior masonry installation has commenced.
 
construction photo
Stage area interior gypsum board installation is ongoing.
 
Friday, January 25, 2019
 
construction photo
Entry canopy framing installation has commenced.
 
construction photo
Interior CMU insulation has commenced.
 
Friday, January 18, 2019
 
construction photo
Window installation has commenced
 
construction photo
Window installation has commenced.
 
Friday, January 11, 2019
 
construction photo
Electrical rough-in is ongoing
 
construction photo
Plumbing rough-in is ongoing.
 
Friday, January 4, 2019
 
construction photoRoof installation is ongoing.
 
construction photo
Site aerial photo.
 
Friday, December 21, 2018
 
construction photo
Mock-up wall panel
 
construction photo
Framing and gypsum board installation
 
Friday, December 14, 2018
 
Construction Photo
TIGER letters have been installed.
 
construction photo
Engineering team reviews drainage on site.
 
Friday, December 7, 2018
 
Hydomulch at entrance to stadium
Hydromulch (grass planting) has
commenced.
 
Interior framing of JH
Interior framing is ongoing.
 
Friday, November 30, 2018
 
JH structural framing
Structural frame installation is wrapping up.
 
photo of stadium
All punch lists have been transmitted to Drymalla.
 
Friday, November 16, 2018
 
football field
Football practice on the new field.
 
Football practice on field.
Football practice on the new field.
 
Friday, November 9, 2018
 
Mechanical rough in.
JH Framing, MEP rough-in, and gyp top out.
 
JH framing, mechanical rough in.
JRHS Framing, MEP rough-in, and gyp top out.
 
Friday, November 2, 2018
 
Drive and striping at stadium.
Stadium drive and striping installation is wrapping up.
 
JH Steel erection is ongoing.
JH steel erection is ongoing.
 
Friday, October 26, 2018
 
junior high under constructionJH erection and wall panel installation is ongoing.
 
metal arriving to construction site
JH steel stud delivery.
 
 
Friday, October 19, 2018
 
construction
JRHS framing and mechanical installation.
 
concession stand
Proposed concession front signage / graphics
 
 
Friday, October 12, 2018
Construction Photo
A mechanical rough-in.
 
Construction Photo
Steel erection is ongoing.
 
 
Friday, September 28, 2018
 
Junior High FrameSteel erection is ongoing. Insulation staged for installation.
 
Track surface
Track surface installation is ongoing.
 
 
Friday, September 21, 2018
 
Construction Photo
Masonry veneer and metal panel installation is ongoing.
 
Construction Photo
Steel Erection is ongoing.
 
Friday, September 14, 2018
 
Photo of SJHS Frame
Area A steel erection is ongoing.
 
Photo of track surfacte
Running track installation has commenced.
Base layer is shown above, which is not the final track color.
 
Friday, September 7, 2018
 
JH Construction PhotoArea A steel erection has commenced.
 
Slab of new jh building
Preparing for Area C concrete placement.
 
Friday, August 31, 2018
 
Chair Backs
Chair back seat installation is wrapping up.
 
Tiger T
Turf installation is nearing completion.
 
Friday, August 24, 2018
 
Concrete pouring    JHRS concrete placement
 
Concrete pour
JRHS concrete placement.
 
 
Friday, August 17, 2018
 
Board on Stadium TurfTurf installation is wrapping up.
 
Junior High foundation
Foundation / slab installation is ongoing.
 
Friday, July 27, 2018
 
Construction Photo
Bleacher installation is ongoing.
 
Construction Photo
 Foundation footing and grade beam excavation is ongoing.
 
Friday, July 20, 2018
 
Construction Photo
Grade beam excavation has begun at the Junior High School.
 
Construction photo

MEP installation is ongoing at the Concession Building.
 
Friday, July 13, 2018
 
Construction Photo
Sturdi Steel installing beams and stringers on home side of stadium
 
Construction Photo

Field event curb installation is ongoing
 
Friday, June 29, 2018
 
Construction Photos
 
Rain has hampered site access.
 
Construction Photo
 
Building pad installation has wrapped up.
 
Friday, June 15, 2018
 
 Construction Photo
 
Concession Restroom building plumbing rough-in.
 
Construction Photo
 
Site drainage underground utilities installation is ongoing.
 
Friday, June 8, 2018
 
Concession Stand photo
Concession Restroom building structure erection is wrapping up.
 
Concession Stand Photo
 Concession Restroom building roof panel installation is ongoing.
 
 
Friday, June 1, 2018
 
Update on construction: earthwork is ongoing, underground utility installation is ongoing, and field drainage and track curb installation has commenced.
 
Connstruction Photo
  
Ticket booth foundation reinforcing has been installed.
 
Construction photo
 
Water line installation is ongoing.
 
 
Friday, May 25, 2018
 
Update on construction: earthwork is ongoing, underground utility installation is ongoing, and field drainage and track curb installation has commenced.
 
Concession Restroom building slab pour.
Concession Restroom building slab pour.
 
Athletic field fine grading is ongoing
Athletic field fine grading is ongoing.
 
Friday, May 18, 2018
 
Update on construction: earthwork is ongoing, underground utility installation is ongoing, and field drainage and track curb installation has commenced.
 
High School driveway connection construction has commenced.
 
Concession restroom building plumbing rough-in and foundation form installation is ongoing.
 
Friday, May 11, 2018
 
Update on construction: earthwork is ongoing, underground utility installation is ongoing, and field drainage and track curb installation has commenced.
 
 
 
 
Friday, May 4, 2018
 
Update on construction: earthwork and underground utility installation is ongoing.

 
Water line installation near Concession-Restroom Building.
 
 
Underground storm line installation.
 
Friday, April 27, 2018
 
Update on construction: earthwork and underground utility installation is ongoing.
 
 
Concession building plumbing.
 
Concession building plumbing.
Friday, April 20, 2018
 
Update on construction: earthwork and underground utility installation is ongoing.
 
Concession building foundation pad installed.
 
Site utility materials staged on site.
 

Friday, April 13, 2018

 

As can be seen by the photos earthwork is in progress. Underground utility installation is ongoing and the building pad installation is wrapping up.

       

 

Moving into the next couple of weeks work will continue on the detention pond, installation of piers for the bleacher installation will begin as will the rough in of slab at the concession stand.