Smithville Independent School District Committed to Excellence

Skip to main content
Mobile Menu
Homecoming is this Friday, September 9th ■ Get Connected with Smithville ISD's Phone App at www.myschoolway.com/smithvilleisd
School Board » Bond 2016 » Construction Updates

Construction Updates

Smithville ISD will post updates in this location as construction on the multi-purpose athletic complex and the new junior high campus begins.
Architectural rendering for the multi-purpose athletic complex with concession and restroom facilities.
(Updated as of November 10, 2017)
 
Construction Updates from PBK
 
Friday, October 19
 
construction
JRHS framing and mechanical installation.
 
concession stand
Proposed concession front signage / graphics
 
 
Friday, October 12
Construction Photo
A mechanical rough-in.
 
Construction Photo
Steel erection is ongoing.
 
 
Friday, September 28
 
Junior High FrameSteel erection is ongoing. Insulation staged for installation.
 
Track surface
Track surface installation is ongoing.
 
 
Friday, September 21
 
Construction Photo
Masonry veneer and metal panel installation is ongoing.
 
Construction Photo
Steel Erection is ongoing.
 
Friday, September 14
 
Photo of SJHS Frame
Area A steel erection is ongoing.
 
Photo of track surfacte
Running track installation has commenced.
Base layer is shown above, which is not the final track color.
 
Friday, September 7
 
JH Construction PhotoArea A steel erection has commenced.
 
Slab of new jh building
Preparing for Area C concrete placement.
 
Friday, August 31
 
Chair Backs
Chair back seat installation is wrapping up.
 
Tiger T
Turf installation is nearing completion.
 
Friday, August 24
 
Concrete pouring    JHRS concrete placement
 
Concrete pour
JRHS concrete placement.
 
 
Friday, August 17
 
Board on Stadium TurfTurf installation is wrapping up.
 
Junior High foundation
Foundation / slab installation is ongoing.
 
Friday, July 27
 
Construction Photo
Bleacher installation is ongoing.
 
Construction Photo
 Foundation footing and grade beam excavation is ongoing.
 
Friday, July 20
 
Construction Photo
Grade beam excavation has begun at the Junior High School.
 
Construction photo

MEP installation is ongoing at the Concession Building.
 
Friday, July 13
 
Construction Photo
Sturdi Steel installing beams and stringers on home side of stadium
 
Construction Photo

Field event curb installation is ongoing
 
Friday, June 29
 
Construction Photos
 
Rain has hampered site access.
 
Construction Photo
 
Building pad installation has wrapped up.
 
Friday, June 15
 
 Construction Photo
 
Concession Restroom building plumbing rough-in.
 
Construction Photo
 
Site drainage underground utilities installation is ongoing.
 
Friday, June 8, 2018
 
Concession Stand photo
Concession Restroom building structure erection is wrapping up.
 
Concession Stand Photo
 Concession Restroom building roof panel installation is ongoing.
 
 
Friday, June 1, 2018
 
Update on construction: earthwork is ongoing, underground utility installation is ongoing, and field drainage and track curb installation has commenced.
 
Connstruction Photo
  
Ticket booth foundation reinforcing has been installed.
 
Construction photo
 
Water line installation is ongoing.
 
 
Friday, May 25, 2018
 
Update on construction: earthwork is ongoing, underground utility installation is ongoing, and field drainage and track curb installation has commenced.
 
Concession Restroom building slab pour.
Concession Restroom building slab pour.
 
Athletic field fine grading is ongoing
Athletic field fine grading is ongoing.
 
Friday, May 18, 2018
 
Update on construction: earthwork is ongoing, underground utility installation is ongoing, and field drainage and track curb installation has commenced.
 
High School driveway connection construction has commenced.
 
Concession restroom building plumbing rough-in and foundation form installation is ongoing.
 
Friday, May 11, 2018
 
Update on construction: earthwork is ongoing, underground utility installation is ongoing, and field drainage and track curb installation has commenced.
 
 
 
 
Friday, May 4, 2018
 
Update on construction: earthwork and underground utility installation is ongoing.

 
Water line installation near Concession-Restroom Building.
 
 
Underground storm line installation.
 
Friday, April 27, 2018
 
Update on construction: earthwork and underground utility installation is ongoing.
 
 
Concession building plumbing.
 
Concession building plumbing.
Friday, April 20
 
Update on construction: earthwork and underground utility installation is ongoing.
 
Concession building foundation pad installed.
 
Site utility materials staged on site.
 

Friday, April 13, 2018

 

As can be seen by the photos earthwork is in progress. Underground utility installation is ongoing and the building pad installation is wrapping up.

       

 

Moving into the next couple of weeks work will continue on the detention pond, installation of piers for the bleacher installation will begin as will the rough in of slab at the concession stand.